This page describes how to setup a Gantt Chart that shows Gantt Calendars functionality.
There are not many differences from the standard Gantt configuration, so we'll note only a few of them that are important for the current configuration.
- Parent Role: select the following roles from the list: affects, inherits from;
- Work Item Types Configuration: add all 4 new WI types with an 'Item' Gantt Presentation Mode and select 'Calendar' as a Parent type for all of them.
- For Data Mapping use custom fields 'from/to'.
The rest of the configuration is up to you, but with just these settings selected, you'll get a nice Gantt for Calendars.
Check also:
- Gantt Calendars main functionality info: click here
- Documentation on how to create the Polarion configuration for the Calendars project: click here
In case of questions please contact [email protected]
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article